Foxfire Pedestrian Bridge & Trail

Foxfire Pedestrian Bridge & Trail

Owner: City of Virginia Beach, Virginia

VCC has been selected as the Prime Contractor for the Foxfire Pedestrian Bridge & Trail project. The work includes the construction of a 10-foot-wide multi-use path from Foxfire Park to the municipal center of Va. Bch. This construction also includes a boardwalk section and a steel bridge to span West Neck Creek.

Status: Under Construction

Nansemond Parkway/Wilroy Road Overpass Over Commonwealth Railway

Nansemond Parkway/Wilroy Road Overpass Over Commonwealth Railway

VCC has been selected as the Prime Contractor for the Nansemond Parkway/ Wilroy Road Overpass project in Suffolk, VA.  This project includes construction of a 220 feet in length bridge structure to span over an existing railroad, building approach embankments for the new bridge structure to include surcharging for settlement, erecting a new signalized traffic intersection, construction of 6,100 feet of new alignment roadway through the corridor.  Construction is scheduled to begin August 2023 and is scheduled to be completed in August 2025.   

Status: Under Construction

Bridge Rd. & Shoulders Hill Rd. Intersection Improvements

VCC has been selected as the Prime Contractor for the Bridge Rd. & Shoulders Hill Rd. Intersection Improvements project in Suffolk, VAThis project has an 18-month duration for constructionScope of work for the project includes roadway improvements, drainage and storm water management, public utilities, traffic signalization, roadway lighting, demolition, traffic control and landscaping.

Status: Under Construction

St. Paul’s Redevelopment – Phase 1

St. Paul’s Redevelopment – Phase 1

Owner: City of Norfolk, Virginia

VirginiaCarolina Civil will be performing infrastructure work for the City of Norfolk, Virginia.  Work includes construction of 2,700 linear feet of new roadway including 2 and 4 lane roadways, wide sidewalk, buffered bicycle lanes, pedestrian accommodations, and a new traffic signal.  The project also includes sanitary sewer, water service, stormwater management, pavement markings, and signage improvements.

Status: Under Construction

P907, Design-Build, Dry Combat Submersible Operations Facility

P907, Design-Build, Dry Combat Submersible Operations Facility

General Contractor: The Whiting-Turner Contracting Company

VirginiaCarolina Civil will be performing site work for WT on JEB Little Creek base in Virginia Beach, Virginia.  Work includes clearing, demolition, grading, water, sewer, and storm drain, asphalt, concrete, signage and pavement markings.

Status: Under Construction

P224 & P999, Design-Build, Operations Support Facility and Training Facility

General Contractor: The Whiting-Turner Contracting Company

VirginiaCarolina Civil will be performing site work for WT on JEB Little Creek base in Virginia Beach, Virginia.  Work includes clearing, demolition, grading, water, sewer, and storm drain, asphalt, concrete, signage and pavement markings.

Status: Under Construction

Pruden Blvd / Prudence Rd Intersection

Pruden Blvd / Prudence Rd Intersection

Owner: City of Suffolk, VA

Scope of work includes heavy utilities, widening of roads, clearing, paving, misc. concrete, and pavement markings.  VCC is the General Contractor.

Status: Under Construction

Burton’s Point Road Reconstruction

Burton’s Point Road Reconstruction

Owner: City of Portsmouth, Virginia

VCC has been selected as the Prime Contractor for Burton’s Point Rd.  The project consists of raising and replacing Burton’s Point Rd. for approximately 1,800 feet to include roadway improvements to Elm Avenue. Scopes of work include clearing & grubbing, demolition, utilities, stone base, grading, erosion & sediment control, curb and gutter, sidewalk, mill and overlay, signage, and electrical work.

Status: Under Construction

Portsmouth Rail to Trail

Portsmouth Rail to Trail

Owner: City of Portsmouth, Virginia

VCC has been selected as the Prime Contractor for the Portsmouth Rail to Trail project.  The project consists of construction of a 1.7-mile-long asphalt trail, to include stormwater features, landscaping, lighting infrastructure, signage, striping, signals, and hardscape amenities.

Status: Under Construction

Edwin Dr. Improvements

Edwin Dr. Improvements

Owner: City of Chesapeake, Virginia

VCC has been selected as the Prime Contractor for the Edwin Dr. Improvements project. The purpose of this project is to convert Edwin Dr. from a one-way road into a two-way roadway. The project will also include new signalization, and reconstruction of the Rte. 168 southbound ramp to accommodate the new two-way traffic operation.

Status: Under Construction

Zone ‘C’ Operations Facility – Phase 1 Early Site Package

Zone ‘C’ Operations Facility – Phase 1 Early Site Package

Owner: City of Suffolk, Virginia

Scope of work includes excavation of a new storm water management pond, drainage pipe, placement of surcharge for future buildings, grading, erosion control, survey, and clearing.

Status: Completed July 2023

Deep Creek Elementary Site Project

Owner: Chesapeake Public Schools

Designer: Timmons Group

VCC will be performing site improvements for Deep Creek Elementary School. Scope of work includes clearing, survey, erosion control, excavation, grading, stone, and concrete work.

Status: Completed September 2022

Greenbrier Parkway & Woodlake Dr. Intersection Improvements

Owner: City of Chesapeake, Virginia

Designer: WSP USA Inc.

Project consists of adding a separate left turn lane and right turn lane along the eastbound approach of Woodlake Dr. at the Greenbrier Parkway intersection, as well as a traffic signal replacement and upgrades to the storm culvert across Greenbrier Parkway.  

Status: Completed April 2023

Crossways Boulevard Improvements

Owner: City of Chesapeake, Virginia

Designer: Kimley-Horn

VirginiaCarolina Civil will be performing infrastructure work for the City of Chesapeake, Virginia.  Work includes erosion control, traffic control, demolition, earthwork and grading, storm drain, miscellaneous concrete, asphalt, signalization, signs and pavement markings.

Status: Completed August 2022

Downtown Suffolk Drainage Improvements

Downtown Suffolk Drainage Improvements

General Contractor: Bridgeman Civil, Inc.

Owner: City of Suffolk, Virginia

Designer: Kimley-Horn

VirginiaCarolina Civil will be performing the stormwater management facility and retaining wall construction for Bridgeman Civil on this project.

Status: Completed October 2022

Water Street Open Space Construction

Owner: City of Norfolk, Virginia

Designer: Stromberg/ Garrigan & Associates

The work under this project consists of site work to include fill material and grading, BMP construction, storm drain and water utility infrastructure construction, hardscaping and landscaping.

Status: Completed October 2021

Portsmouth Seawall Area 6 Replacement

General Contractor: Crofton Industries

Owner: City of Portsmouth, Virginia

Designer: McPherson Design Group

VirginiaCarolina Civils’ scope of work includes survey, erosion control, clearing, demolition, earthwork for site work and structural work, utilities, and grading.

Status: Completed June 2023

Chesapeake Trail

Owner: City of Chesapeake, Virginia

Designer: City of Chesapeake

This project consists of converting an existing railroad right of way into a pedestrian/ bicycle path. Scope of work includes survey, erosion control, clearing, earthwork, utilities, misc. concrete, new pavement, pavement markings and installation of a precast bridge structure.

Status: Completed August 2021

Club House Road Drainage Improvements

Owner: City of Virginia Beach, Virginia

Designer: Michael Baker International

Installation of Storm Drain, Water Main, Gravity Sewer, Sewer Force Main, Roadway Reconstruction, construction of stormwater pond and golf course modifications.

Status: Completed September 2022

Wood Street Roadway and Utility Improvements

Owner: City of Norfolk, Virginia

Designer: Timmons Group

The Work under this project consists of the construction of new stormwater conveyance pipes and structures, roadway demolition and reconstruction, curb and gutter, sidewalk, curb ramp upgrades, and both public and private utilities.

Status: Completed March 2022